YIELD OF CONCRETE...

How to measure yield of concrete at site and plant... to measure how much actual volume of concrete dispatched and rectification if yield is minimum and maxmimum.


TO MEASURE YIELD FOLLOWING APPARATUS REQUIRE:

Cylinder - 10 ltr capacity

Tamping rod

Balace - 100 kg capacity

scoop, wheel barrow etc.

Procedure

1) Determine the actual volume of 10 ltr cylinder by filling it by distill water after taking tare wt. of cylinder, after derive water wt. by subtracting total wt. of cylinder and water with cylinder wt. devide it from density of water which is 1000 kg/ m3. Hence we get actual volume of cylinder.

2) Fill the concrete in cylinder thickness of one layer  is 50 mm and tamping must not less than 60 times in the case of 10 ltrs cylinder, fill the cylinder by repeat above procedure, strike excessive concrete from cylinder and side of cylinder must be tamped 10 to 15 times so that no large bubble appears on the surface.

3) Determine wt. of concrete in cylinder by subtracting total weight to cylinder tare weight.

4) Apply formula :
   
      density = mass of concrete / volume of            cylinder

Let mass of concrete= 24.040 kg
and volume of cylinder = 0.01 m3
  Than density of concrete
       
            24.040/ 0.01 = 2404 kg/m3

THAN YIELD OF CONCRETE

 Theoretical density/ Practical density

we derive practical density above which is
2404 kg / m3

For theoretical density we need batchsheet which is come during dispatch of concrete
Let total quantity of concrete dispatched is 5 m3 and weight of concrete is 12500 kg for 5m3 concrete as per batchsheet.

Than Theoritical density is

      12500/ 5 = 2500 kg / m3

Hence yield =  2500/2404
                       =   1.03

SO THAT OUR YIELD IS 1.03 WHICH INDICATES WE  GIVE MORE CONCRETE

AND HOW MUCH IS GIVEN BELOW

= 1.03 × 5 = 5.15 m3
i.e we produce 0.15 m3 more in the case of 5 m3 concrete.

Yield of concrete must be between
0.98  to 1.02

Cause of more volume of concrete is low specific gravity of aggregate and may also due to problem in calibration of plant.

To rectify this we can reduce quantity of aggregate in mix design .



     



1 comment:

  1. Hi there to everybody, it’s my first go to see of this web site; this weblog consists of awesome and in fact good stuff for visitors. Hurrah, that’s what I was exploring for, what stuff! Existing here at this blog, thanks admin of this web site. You can also visit Concrete Resurfacing for more Sydney Wide Spray Pave related information and knowledge.

    ReplyDelete

CONCRETING BY VOLUME BATCHING AT SITE ....

HOW  WE   DO   CONCRETE   BY   VOLUME   BATCHING  AT SITE .... There are two methods of batching of concrete 1) By weigh  batching- In ...

PACE RATE OF CTM