PACE RATE OF COMPRESSIVE TESTING MACHINE

As per Indian standard 516 pace rate of C. T. M must be 140 kg/cm 2/minute.  so what is meaning of this given below:

surface area of cube 15 cm dimension= 225 cm 2

so in one minute load applied on cube :140*225=31500 kg/minute
Than in one second it is : 31500/60=525 kg/second

one kilogram = 9.81 N (10 Newton)
so                  = 525*10= 5250 N/second

one newton= 0.001 kn

                  =5250*0.001=5.25 kn/second


If we use 10 cm cube than in this case surface area change and we calculate it will be come 2.33 kn/second.

6 comments:

  1. Wonderful article, which you have shared here . Your article very informative and useful to know more about the features.Concrete contractors San Antonio

    ReplyDelete
  2. This is excellent information which is shared by you. This information is meaningful and magnificent for us to increase our knowledge about it. Keep sharing this kind of information. Thank you. Concrete Puming Edmonton

    ReplyDelete
  3. I am very much thankful to you for sharing this essential knowledge. This information is very helpful for everyone. So please always share this kind of information. Thanks once again for sharing it. Structural Engineering Design Services

    ReplyDelete
  4. A very delightful article that you have shared here. Your blog is a valuable and engaging article for us, and also I will share it with my companions who need this info. Structural Engineering Thankful to you for sharing an article like this.

    ReplyDelete
  5. It is what I was searching for is really informative. It is a significant and useful article for us. engineering consulting firms Thankful to you for sharing an article like this.

    ReplyDelete
  6. The content you've posted here is fantastic because it provides some excellent information that will be quite beneficial to me. Thank you for sharing about consulting companies. Keep up the good work.

    ReplyDelete

CONCRETING BY VOLUME BATCHING AT SITE ....

HOW  WE   DO   CONCRETE   BY   VOLUME   BATCHING  AT SITE .... There are two methods of batching of concrete 1) By weigh  batching- In ...

PACE RATE OF CTM